Hardware options installation 32
4.
Install the hard drive.
5. Determine the status of the hard drive from the hot-plug SAS hard drive LED combinations ("Hot-plug
SATA or SAS hard drive LEDs" on page 8).
6. Install the bezel.
7. Resume normal server operations.
SATA optical drive
For clarity, the following illustrations include option cabling only.
CAUTION: To prevent improper cooling and thermal damage, do not operate the server unless
all bays are populated with either a component or a blank.
To install the component:
1. Power down the server (on page 17).
2. Remove the bezel (on page 18).
3. Remove the access panel (on page 19).
4. Remove the applicable media bay blank ("Remove a media bay blank" on page 20).
Vedere la pagina 31